LUTHAI TAN CHAU SPINNING MILL

  • Vị trí dự án Tan Hoi Industrial Cluster, Tan Chau District, Tay Ninh Province
  • Client Lu Thai (Vietnam) Co., Ltd.
  • Package Construction of structural works, finishing, and MEP systems for the spinning workshop, cotton warehouse, yarn warehouse, auxiliary works, and infrastructure of Zone A
  • Tổng diện tích sàn xây dựng (CFA) 26.000 m²
  • Implementation time 01/2019 – 07/2019
1
Story
26.000
m2
Project information

The Luthai Tan Chau Spinning Mill project, invested by Lu Thai (Vietnam) Co., Ltd., is located at Tan Hoi Industrial Cluster, Tan Chau District, Tay Ninh Province.

The project consists of a single-story facility with a total construction floor area of 26,000 m², including a spinning workshop, cotton warehouse, yarn warehouse, as well as auxiliary works and infrastructure for Zone A.

Phuoc Thanh was responsible for structural works, finishing, and MEP systems. The project commenced in January 2019 and was completed in July 2019, ensuring the investor’s requirements for schedule, quality, and technical standards.

The project contributes to enhancing yarn production capacity, meeting export demands, and promoting the textile industry in Tay Ninh Province.

Other projects

SAILUN VIETNAM FACTORY EXPANSION – PHASE 2 & PHASE 3
SAILUN VIETNAM FACTORY EXPANSION – PHASE 2 & PHASE 3
Phuoc Thanh executed construction, finishing, and MEP works for the Sailun Vietnam Factory Expansion – Phase 2 & Phase 3, a 1-storey building with a total floor area of 98,000 m² in Go Dau, Tay Ninh; commenced in 02/2021 and completed in 07/2023, contributing to enhancing tire production and export capacity in Vietnam.
RADIAN JINYU (VIETNAM) TIRE FACTORY – PHASE 1
RADIAN JINYU (VIETNAM) TIRE FACTORY – PHASE 1
Phuoc Thanh executed construction, finishing, and MEP works for the Radian Jinyu (Vietnam) Tire Factory – Phase 1, a 2-storey building with a total floor area of 19,250 m² at Phuoc Dong Industrial Park, Tay Ninh; commenced in 06/2020 and completed in 11/2020, meeting technical standards and schedule, contributing to the enhancement of local industrial production capacity.
JINYU TIRE FACTORY
JINYU TIRE FACTORY
Phuoc Thanh acted as the general contractor for construction, finishing, and MEP works of the JINYU TIRE Factory – a 2-storey project with a total floor area of 19,250 m² at Phuoc Dong Industrial Park, Tay Ninh, commenced in 06/2020 and completed in 11/2020.
HAILIDE VIETNAM FABRIC WORKSHOP
HAILIDE VIETNAM FABRIC WORKSHOP
Hailide Vietnam Fabric Workshop – a 74,588 m² civil construction project in Phuoc Dong Industrial Park, Tay Ninh, executed by Phuoc Thanh, including functional buildings and synchronized infrastructure.
Request a Consultation

    Please fill out the form below, and the Phuoc Thanh team will respond to your email as soon as possible.