KIM TIN MDF CHON THANH ARTIFICIAL BOARD MANUFACTURING PLANT

  • Vị trí dự án Lot A25-B, N25 Street, Becamex – Binh Phuoc Industrial Park, Minh Thanh Commune, Chon Thanh District, Binh Phuoc Province
  • Client Kim Tin MDF Chon Thanh Joint Stock Company
  • Package Construction, finishing, and MEP systems
  • Tổng diện tích sàn xây dựng (CFA) 55.000 m2
  • Implementation time February 2023 – October 2023
55.000
m² of floor area
438.000
m³ of MDF boards per year
Project information

The Kim Tin MDF Chon Thanh artificial board manufacturing plant is one of the key industrial projects in Binh Phuoc Province constructed by Phuoc Thanh.

With a designed production capacity of 438,000 m³ of MDF boards per year and an integrated rental factory area, the project aims to expand production capacity and enhance the value of the wood processing industry in the region.

Phuoc Thanh was in charge of the entire construction, finishing, and MEP systems for the facility, with a total floor area of 55,000 m², ensuring strict adherence to schedule and technical standards for one of the largest interior material production complexes in Southern Vietnam.

Other projects

SAILUN VIETNAM FACTORY EXPANSION – PHASE 2 & PHASE 3
SAILUN VIETNAM FACTORY EXPANSION – PHASE 2 & PHASE 3
Phuoc Thanh executed construction, finishing, and MEP works for the Sailun Vietnam Factory Expansion – Phase 2 & Phase 3, a 1-storey building with a total floor area of 98,000 m² in Go Dau, Tay Ninh; commenced in 02/2021 and completed in 07/2023, contributing to enhancing tire production and export capacity in Vietnam.
RADIAN JINYU (VIETNAM) TIRE FACTORY – PHASE 1
RADIAN JINYU (VIETNAM) TIRE FACTORY – PHASE 1
Phuoc Thanh executed construction, finishing, and MEP works for the Radian Jinyu (Vietnam) Tire Factory – Phase 1, a 2-storey building with a total floor area of 19,250 m² at Phuoc Dong Industrial Park, Tay Ninh; commenced in 06/2020 and completed in 11/2020, meeting technical standards and schedule, contributing to the enhancement of local industrial production capacity.
JINYU TIRE FACTORY
JINYU TIRE FACTORY
Phuoc Thanh acted as the general contractor for construction, finishing, and MEP works of the JINYU TIRE Factory – a 2-storey project with a total floor area of 19,250 m² at Phuoc Dong Industrial Park, Tay Ninh, commenced in 06/2020 and completed in 11/2020.
HAILIDE VIETNAM FABRIC WORKSHOP
HAILIDE VIETNAM FABRIC WORKSHOP
Hailide Vietnam Fabric Workshop – a 74,588 m² civil construction project in Phuoc Dong Industrial Park, Tay Ninh, executed by Phuoc Thanh, including functional buildings and synchronized infrastructure.