JINYU TIRE FACTORY

  • Vị trí dự án Phuoc Dong Industrial Park, Tay Ninh Province
  • Client JINYU (Vietnam) Tire Co., Ltd.
  • Package Construction, finishing, and MEP works
  • Tổng diện tích sàn xây dựng (CFA) 19,250 m²
  • Implementation time 06/2020 – 11/2020
2
Floors
Project information

The JINYU TIRE Factory Project, invested by JINYU (Vietnam) Tire Co., Ltd., is located in Phuoc Dong Industrial Park, Tay Ninh Province.

The development comprises 2 floors, with a total construction floor area of 19,250 m², aiming to expand tire production capacity to meet both domestic and international market demands.

Phuoc Thanh served as the general contractor for construction, finishing, and MEP works, commenced in 06/2020 and completed in 11/2020, fulfilling all requirements in terms of schedule, quality, and technical standards.

The project contributes to enhancing tire production capacity and promoting economic growth in Tay Ninh Province.

Other projects

SAILUN VIETNAM FACTORY EXPANSION – PHASE 2 & PHASE 3
SAILUN VIETNAM FACTORY EXPANSION – PHASE 2 & PHASE 3
Phuoc Thanh executed construction, finishing, and MEP works for the Sailun Vietnam Factory Expansion – Phase 2 & Phase 3, a 1-storey building with a total floor area of 98,000 m² in Go Dau, Tay Ninh; commenced in 02/2021 and completed in 07/2023, contributing to enhancing tire production and export capacity in Vietnam.
RADIAN JINYU (VIETNAM) TIRE FACTORY – PHASE 1
RADIAN JINYU (VIETNAM) TIRE FACTORY – PHASE 1
Phuoc Thanh executed construction, finishing, and MEP works for the Radian Jinyu (Vietnam) Tire Factory – Phase 1, a 2-storey building with a total floor area of 19,250 m² at Phuoc Dong Industrial Park, Tay Ninh; commenced in 06/2020 and completed in 11/2020, meeting technical standards and schedule, contributing to the enhancement of local industrial production capacity.
HAILIDE VIETNAM FABRIC WORKSHOP
HAILIDE VIETNAM FABRIC WORKSHOP
Hailide Vietnam Fabric Workshop – a 74,588 m² civil construction project in Phuoc Dong Industrial Park, Tay Ninh, executed by Phuoc Thanh, including functional buildings and synchronized infrastructure.
HLI ECOHUB NAM HA FACTORY
HLI ECOHUB NAM HA FACTORY
Phuoc Thanh executes structural, MEP, and infrastructure works for the HLI Ecohub Nam Ha Factory in Binh Thuan, comprising six factories on a 42,902 m² site, contributing to local socio-economic growth.
Request a Consultation

    Please fill out the form below, and the Phuoc Thanh team will respond to your email as soon as possible.