DAIRY FARMING AND MILK PROCESSING COMPLEX PROJECT

  • Vị trí dự án Hung Thuan Commune, Trang Bang Town, Tay Ninh Province
  • Client Agromilk Tay Ninh Joint Stock Company
  • Package Construction, M&E, and infrastructure works
  • Tổng diện tích sàn xây dựng (CFA) 59.658 m²
  • Implementation time 04/2023 – 08/2023
59.658
m2
Project information

The Dairy Farming and Milk Processing Complex Project, invested by Agromilk Tay Ninh Joint Stock Company, is located in Hung Thuan Commune, Trang Bang Town, Tay Ninh Province.
The facility has 2 storeys with a total gross floor area of 59,658 m², comprising civil works, infrastructure, and mechanical & electrical (M&E) systems.

Phuoc Thanh undertook the construction and M&E infrastructure package, commencing in April 2023 and completing in August 2023, ensuring schedule, quality, and technical standards as required by the client.

The project contributes to the sustainable development of the dairy farming industry, enhances milk processing capacity, and creates additional employment for the local workforce.

Other projects

SAILUN VIETNAM FACTORY EXPANSION – PHASE 2 & PHASE 3
SAILUN VIETNAM FACTORY EXPANSION – PHASE 2 & PHASE 3
Phuoc Thanh executed construction, finishing, and MEP works for the Sailun Vietnam Factory Expansion – Phase 2 & Phase 3, a 1-storey building with a total floor area of 98,000 m² in Go Dau, Tay Ninh; commenced in 02/2021 and completed in 07/2023, contributing to enhancing tire production and export capacity in Vietnam.
RADIAN JINYU (VIETNAM) TIRE FACTORY – PHASE 1
RADIAN JINYU (VIETNAM) TIRE FACTORY – PHASE 1
Phuoc Thanh executed construction, finishing, and MEP works for the Radian Jinyu (Vietnam) Tire Factory – Phase 1, a 2-storey building with a total floor area of 19,250 m² at Phuoc Dong Industrial Park, Tay Ninh; commenced in 06/2020 and completed in 11/2020, meeting technical standards and schedule, contributing to the enhancement of local industrial production capacity.
JINYU TIRE FACTORY
JINYU TIRE FACTORY
Phuoc Thanh acted as the general contractor for construction, finishing, and MEP works of the JINYU TIRE Factory – a 2-storey project with a total floor area of 19,250 m² at Phuoc Dong Industrial Park, Tay Ninh, commenced in 06/2020 and completed in 11/2020.
HAILIDE VIETNAM FABRIC WORKSHOP
HAILIDE VIETNAM FABRIC WORKSHOP
Hailide Vietnam Fabric Workshop – a 74,588 m² civil construction project in Phuoc Dong Industrial Park, Tay Ninh, executed by Phuoc Thanh, including functional buildings and synchronized infrastructure.
Request a Consultation

    Please fill out the form below, and the Phuoc Thanh team will respond to your email as soon as possible.