BINH CHIEU LOT H – TDH RIVERVIEW APARTMENT COMPLEX

  • Vị trí dự án Frontage of Street No. 6 & Ngo Chi Quoc Street, Binh Chieu Ward, Thu Duc District, Ho Chi Minh City
  • Client Thu Duc Housing Development Corporation (Thu Duc House)
  • Package Structural frame and architectural works
  • Tổng diện tích sàn xây dựng (CFA) 21,000 m²
  • Implementation time 11 Sept 2018 – Oct 2019
17
Storeys above ground
1
Basement level
216
Apartments
Project information

The Binh Chieu Lot H – TDH Riverview Apartment Complex is invested by Thu Duc Housing Development Corporation (Thu Duc House). It is located at the frontage of Street No. 6 and Ngo Chi Quoc Street, Binh Chieu Ward, Thu Duc District, Ho Chi Minh City.

The project comprises 17 above-ground storeys and 1 basement level, with a total gross floor area of 21,000 m². It is master-planned to meet the growing residential demand in the northeastern gateway of the city.

Phuoc Thanh Construction undertook the structural frame and architectural works package, commencing on 11 September 2018 and completing in October 2019. Throughout execution, Phuoc Thanh strictly adhered to technical standards to ensure quality, schedule compliance, and occupational safety.

The completed development contributes to the supply of high-quality housing in Ho Chi Minh City and reaffirms Phuoc Thanh’s reputation and capability in high-rise residential construction.

Other projects

SAILUN VIETNAM FACTORY EXPANSION – PHASE 2 & PHASE 3
SAILUN VIETNAM FACTORY EXPANSION – PHASE 2 & PHASE 3
Phuoc Thanh executed construction, finishing, and MEP works for the Sailun Vietnam Factory Expansion – Phase 2 & Phase 3, a 1-storey building with a total floor area of 98,000 m² in Go Dau, Tay Ninh; commenced in 02/2021 and completed in 07/2023, contributing to enhancing tire production and export capacity in Vietnam.
RADIAN JINYU (VIETNAM) TIRE FACTORY – PHASE 1
RADIAN JINYU (VIETNAM) TIRE FACTORY – PHASE 1
Phuoc Thanh executed construction, finishing, and MEP works for the Radian Jinyu (Vietnam) Tire Factory – Phase 1, a 2-storey building with a total floor area of 19,250 m² at Phuoc Dong Industrial Park, Tay Ninh; commenced in 06/2020 and completed in 11/2020, meeting technical standards and schedule, contributing to the enhancement of local industrial production capacity.
JINYU TIRE FACTORY
JINYU TIRE FACTORY
Phuoc Thanh acted as the general contractor for construction, finishing, and MEP works of the JINYU TIRE Factory – a 2-storey project with a total floor area of 19,250 m² at Phuoc Dong Industrial Park, Tay Ninh, commenced in 06/2020 and completed in 11/2020.
HAILIDE VIETNAM FABRIC WORKSHOP
HAILIDE VIETNAM FABRIC WORKSHOP
Hailide Vietnam Fabric Workshop – a 74,588 m² civil construction project in Phuoc Dong Industrial Park, Tay Ninh, executed by Phuoc Thanh, including functional buildings and synchronized infrastructure.